Baseline
Short answer
A baseline is the approved version of a project’s scope, schedule or budget, frozen at a set point, often at a planning gate. Actual progress is compared with it, so slips show up as a variance instead of being quietly overwritten in the plan.
Why it matters
Without a baseline, moving a date in the plan erases the evidence that anything slipped. With one, every change is visible as the difference between the baseline and the current plan.
Re-baselining
Re-baselining is sometimes right, for example after an approved change request. It should be a recorded decision, and the original baseline should stay on record.