Earned value
Short answer
Earned value management (EVM) measures project performance by comparing three things: the planned value of work scheduled, the earned value of work actually completed, and the actual cost. From them it derives schedule and cost variances and performance indices.
The three measures
- Planned value (PV): the budgeted cost of the work scheduled to date.
- Earned value (EV): the budgeted cost of the work actually completed.
- Actual cost (AC): what the completed work actually cost.
The main indicators
- Schedule variance = EV − PV; schedule performance index (SPI) = EV ÷ PV.
- Cost variance = EV − AC; cost performance index (CPI) = EV ÷ AC.
An index below 1 means behind schedule (SPI) or over budget (CPI).