Tip

Write RAID entries a sponsor will actually read

Short answer

Write every RAID entry as cause, event and impact in one sentence, give it one owner and a date, and say what decision you need. If an entry asks nothing of anyone, it is a note, not a risk.

1. Use cause, event, impact

Weak: “Vendor risk.” Strong: “Because the vendor has not confirmed API access (cause), integration testing may start late (event), delaying go-live by two to three weeks (impact).”

2. One owner, a named person

A team is not an owner. If nobody will lose sleep over it, nobody will act on it.

3. A date, always

A review date for risks, a resolve-by date for issues. Entries without dates get read once and then never again.

4. Say what you need

End with the ask: “Decision needed: approve 40,000 (in our budget currency) for a second vendor by 30 Oct.” Sponsors act on asks, not on descriptions.

5. Close entries out loud

When a risk is closed or becomes an issue, say so in the next report. Silent closures make the log look like a graveyard and teach people to ignore it.